Active Infrastructure Projects

Almeda Genoa Road Improvements

Mykawa Road to Telephone Road

Project Scope: Mill & Overlay
Location: Almeda Genoa Rd. between Mykawa Rd. and Telephone Rd.
Construction Begins: June 15, 2026
Estimated Duration: 25 working days
Contractor: SER Construction Partners, LLC
Project Contact: Adrian Carter, Project Manager, 713-829-0260

Please use caution in the area and expect construction activity during the project period.

District D Project Alert - Almeda Genoa Road Improvements

Click the image above to view the full project alert.

Calumet St. Improvements

Austin St. to SH 288

Project Scope: Mill & Overlay
Location: Calumet St. between Austin St. and SH 288
Construction Begins: May 20, 2026
Estimated Duration: 20 working days; around June 17, 2026
Contractor: Durwood Greene Construction Co.
Project Contact: Alissa Hardy, Project Manager, 832-727-2248

Please use caution in the area and expect construction activity during the project period.

District D Project Alert - Calumet St. Improvements

Click the image above to view the full project alert.


Completed Infrastructure Projects

No completed projects listed at this time. Completed projects will be archived here.


Project Contact Information

For questions regarding projects listed on this page, please contact:

Corey Glenn
Chief of Staff
Houston City Council District D
Office of Council Member Dr. Carolyn Evans-Shabazz
Phone: 832.393.3202
900 Bagby St., 1st Floor, Houston, TX 77002
Email: Corey.Glenn@houstontx.gov